home
project history
whats new
project maps
public meetings
environmental process
related links
faqs
newsletter
mailing list
contact info
 
 
PROJECT HISTORY


SUMMARY OF PAST ACTIVITY
1992 – 1994
  US 93, Somers to West of Whitefish Environmental Impact Statement (EIS) considers alternatives for US 93. The EIS combined several ongoing and planned projects from Somers to Whitefish, including the Kalispell Bypass. An Advisory Committee is established to guide the process.

1993
  The Kalispell Transportation Plan and Bypass Feasibility Study issued in October recommends westside bypass around Kalispell.

1994
  FEIS recommends western bypass around Kalispell as preferred alternative.
  Record of Decision (ROD) on US 93, Somers to West of Whitefish approved in November. Alternative B (West Kalispell Bypass) is included in ROD as the preferred alternative.

1995
  MDT identifies six of the projects covered in the FEIS to begin design work.

1996
    MDT begins design on the six projects including preliminary design for corridor preservation on the Kalispell Bypass. Several revisions to the Bypass alignment shown in the FEIS are proposed based on community input.
 US 93 (Montana 40 – South & Grandview North) projects awarded for construction in April.

1997
  MDT and FHWA approve right-of-way plans for the Kalispell Bypass based upon the Corridor Preservation plans. Plans are placed on file at the Flathead County Courthouse in February and right-of-way acquisition begins.
  US 93 (Montana 40 - North) project awarded for construction in June.

1999
  US 93 (Somers - Ashley Creek - South) project awarded for construction in June.

2000
 US 93 (Somers - Ashley Creek - North) project awarded for construction in May.

2003
  MDT begins design of the US 93, Whitefish Urban area.

2004
  US 93 (Ashley Creek – Kalispell) project awarded for construction
in February.
  In June, MDT begins re-evaluation of the Kalispell Bypass portion of the 1994 FEIS and begins preliminary design for the Bypass.
  Kalispell Bypass kickoff meeting in June to familiarize community with project.
  Kalispell Bypass public scoping meeting in August to identify potential issues
  Montana Transportation Commission approves Limited Access Resolution for Bypass in August.

2006
  REIS for Kalispell Bypass was signed in July 2006. Environmental impacts were disclosed at the August 2005 public meeting and there have been no new significant environmental issues raised. The NEPA re-evaluation process is completed with signature of the re-evaluation of the Environmental Document.
  Public meetings were held in May & July 2006 to discuss the project phasing. MDT selected the first segment for construction in September 2006, based upon community and agency comments and recommendations (MDT Press Release).

2007
  Reserve-Loop portion is built
  Neighboorhood meetings held for noise mitigation discussions
  Right-of-way moves to active acquisition

2008
  Final design is being completed for entire project
  Right-of-way continues to be acquired, with emphasis on lands south of US 2 (south segment)
 

Summary of All Past Activity

Sep 1994 "Somers to Whitefish EIS"

1994
"MDT implements ROD"


Aug 1997
"MTC passes resolution"


early 2004
"2030 adjustments
"

Jul 2006
"Re-evaluation complete"


Sep 2006
"City & County request"


Fall 2007
"Reserve Loop completed"


Fall 2007
"City & County continue south segment priority"